BUILDING THE
VISION UPDATE

  • March 18th: Ground floor "Chapel" Use and Occupancy (U & O) application submitted to (PG-DPIE) Department of Permitting, Inspection & Enforcement
  • April 14th: Application returned to us by DPIE with comments
  • Currently: Our Architect is addressing the comments for resubmitting
  • Projected date for resubmitting: May or June 2015
2008 Land Acquisition
Hired Civil Engineer:  Landesign
  • Stormwater Management Concept Plan
  • Grading, Erosion & Sediment Control Plan
  • Site and Landscape Plans
  • Street Tree and Lighting Plan
  • Maintenance of Traffic and Stripping Plan
  • Type 2 Tree Conservation Plan
  • Building, Retaining Wall Permits 
  • Commercial Driveway Entrance Permit
  • Cost Estimate for Site Work
Conceptual Site Plan
Land Acquisition
(Current Worship Facility)

Construction
GOALS

Obtained:
2014 Construction Activity
Hired Architect: The Building Ideas Group, LLC
Obtained:
  • Conceptual Design Phase
  • Schematic Design Phase
  • Color Pictorial Rendering
Color Pictorial Rendering
(Future Edifice)
Aerial View
Main Floor Plan
  • Obtain County approval on Building Plans
  • Obtain cost estimate for first phase construction
  • Obtain construction loan
  • Complete preliminary construction that will allow us to have Sunday service at the Brook (June 2015)
  • Complete first phase construction
    (December 2015 / January 2016)